A hospital mass casualty exercise using city buses and a tent as a hybrid system for patient decontamination.
Аннотация
OBJECTIVE
A hospital mass casualty simulation exercise testing feasibility of two city buses and a tent as a hybrid system for patient decontamination.
DESIGN
Observational study of a single mass casualty simulation exercise involving patient decontamination
SETTING
Held on May 26, 2016 at the Montreal General Hospital, a Level 1 Trauma center without a garage.
PATIENTS,
PARTICIPANTS
Twenty-one medical staff including nurses, doctors, and patient attendants, and 30 volunteer-simulated patients.
INTERVENTIONS: The foregrounds of the hospital were cordoned off to create a single-entry point for the simulated patients that were identified as contaminated (C) by staff wearing personal protective equipment. Non-contaminated patients were directed to a separate hospital entrance. C patients were triaged in Bus 1 to determine priority for decontamination. Bus 2 served as a holding area for stable patients awaiting decontamination. Patients were decontaminated in appropriate tent sections (non-ambulatory, ambulatory male or female) and then directed to the emergency department.
RESULTS
Direct observation and participant feedback suggested that buses may provide adequate shelter for C patients. However, buses had limited capacity for non-ambulatory patients, who were not easily transported inside. Furthermore, areas of improvement were identified in communication, staffing, equipment, and coordination of operations.
CONCLUSIONS
The use of city buses as triage and waiting zones prior to decontamination appears feasible for centers without a garage and facing unpredictable weather conditions. Further simulations are required for fine-tuning and testing real-time unfolding of tasks, ideally during an unannounced exercise.
Предметные рубрики MeSH
Подготовка и перевод публикации
Обработка статьи · этапы, ошибки и управление
Ошибки и ограничения
История · было → стало
Состояние обновляется каждые 5 секунд, пока блок открыт. Процент показывается только там, где известен объём работы. Пауза останавливает продолжение этапа; текущий запрос к источнику может завершиться.
Тип публикации указан по данным источника. Уровень доказательности автоматически не присваивается.